昨日ヴァレーから戻りました。
ヴァレー内はいたるところで道路工事をやっていて、ヨセミテヴィレッジ〜センチネル橋間が通行止めでした。そのためにカリービレッジ〜ヨセミテヴィレッジ間で恒常的に渋滞が発生していて、これには参りました。


YOSEMITE VALLEY ROADS (Various Repair Locations–Most of the work will occur at various areas on Southside Drive and Northside Drive between Bank 3-way and Camp-6 intersection)
June 6th thru June 10th Continue Microseal (Were trying to keep the delays under 15-minutes when we are working on the 2-way road sections. Most of the Southside Drive work will occur between El Capitan Crossover and Swinging Bridge, as well as at the south end of the Sentinel Bridge. We’ll also be working again on Northside Drive between Bank 3-Way and Camp-6 and possibly a few other areas (work in the other areas is dependent upon how work progresses throughout the week). No further microseal work is scheduled after June 10th.
***June 8th thru June 10th Microseal one lane of Northsdrive between El Captian Crossover and Pohono Bridge – one lane of traffice will remain open at all times.
June 13th and beyond There may be some asphalt overlay and patching work in a few small areas at various locations throughout the summer
During 6:00 AM to 8:00 AM and 4:00 PM to 6:00 PM (commuter hours) Monday thru Friday, the delays will be kept to 15-minutes maximum. Also, the hours of work with 30-minute delays may vary from day to day depending upon the weather and traffic conditions
SOUTH FORK BRIDGE REPLACEMENT
June 6th thru June 10th Complete Bridge Demolition (This may be a bit optimistic, but they are planning to have the majority of the bridge demolition completed on June 10th–however they are planning to leave parts of the piers for the new bridge falsework support) (There may be some minimal delays moving equipment and trucks in and out of the site.)
June 13th thru June 17th Begin excavation and formwork for the new abutments.