タイオガ&グレイシャーポイントロード除雪状況

タイオガロードはクレーンフラットから15マイル。
グレイシャーポイントロードはすでに管理車両は通行しているようで、倒木処理などが行われています。こちらのほうは開通の日が近いのかもしれません。
最新情報は★園内除雪作業進行状況からもご確認ください。
*************************************************
Update on Tioga road Opening 4/24/08.
Tioga Road opening operations continued yesterday.
Tioga Road progress for April 23, 2008:
Starting Location: 11.3 miles from Crane Flat Gate
Ending Location:15 miles from Crane Flat Gate (Mc Swain Summit)
Distance plowed today: 3.7miles
Average Snow depth: 6 ft.
Update on Glacier Point Road 4/24/08
Glacier Point Road is open to Administrative Traffic only.
The road is very icy due to current spring temperatures and is not sanded.
Wawona Road crews will be performing shoulder and road repairs as needed from Chinquapin to Glacier Point.
The gate at Chinquapin will be closed for administrative traffic only. ( Contact 460 before Admin. traffic entersroadway).
Forestry crews are presently removing hazard trees on the Glacier Point road starting at Chinquapin to Glacier Point.
Please watch out for Road crews, Sign Shop and Forestry crews on roadway drive slow and drive defensively. (T.Brochini – 4/24/08)

タイオガロード除雪状況

タイオガロード除雪状況が発表されています。4/22現在クレーンフラットから12.4マイル地点だそうです。
最新情報は★園内除雪作業進行状況からもご確認ください。
*************************************************
Tioga Road Opening progress
Status of Tioga Road opening ending on 4/22/08.
Progress report:
April 21, 2008
Tioga Road progress for April 21, 2008
Starting Location: Crane Flat Gate
Ending Location:7.2 miles from Crane Flat Gate (South Fork Bridge)
Distance plowed today:7.2 miles
Snow depth: 4-5 ft.
April 22,2008
Tioga Road opening operations continued yesterday.
Tioga Road progress for April 22, 2008
Starting Location: South Fork Bridge
Ending Location:12.4 miles from Crane Flat Gate
Distance plowed today:5.2 miles
Average Snow depth: 5 ft. 9 (T. Brochini – 4/23/08)

バジャーパススキー場は3月30日で営業終了

バジャーパススキー場は3月30日で営業終了です。
また4月13日まではスキー場パーキングまでアプローチできます。(クロスカントリースキー、スノーシューなどがまだ楽しめます)14日からはグレイシャーポイントロードの除雪作業のため、Chinquapinのゲート(Wawona roadとGP roadの分岐)がクローズとなります。

Special Note: Badger Pass ski area will close on March 30th, 2008. Weather permitting – the road will remain open from Chinquapin to the Badger Pass parking lot until April 13th. The gate at Chinquapin will be closed to all traffic for snowplow operations to begin April 14th on the Glacier Point road

Badger Passスキー場情報

Badger Pass Snow Conditions:
BASE DEPTH: 22 – 34 inches
NEW SNOW (last 24 hours): 1″
SURFACE CONDITIONS: Powder/Packed Powder
FORECAST: Chance snow
TEMPS: Highs in the upper – 20s. Lows in teens.
*************************************************
Badger Pass is open. Food Service opens at 8:00 a.m.; Tickets, Rentals, Ski and Snowboard School, and Cross-Country
8:30 a.m.; Lifts and Sport Shop 9:00 a.m. For the most up to date snow conditions call 372-1000. (A. Catamec – 12/19/07)

Badger Passスキー場のオープン

Badger Passスキー場が20日から今シーズンの営業をオープンします。
例年は3月末〜4月上旬の週末まで営業します。
Badger Pass is scheduled to open to the public commencing Thursday, December 20. Food Service opens at 8:00 a.
m.; Tickets, Rentals, Ski and Snowboard School, and Cross-Country 8:30 a.m.; Lifts and Sport Shop 9:00 a.m. For the
most up to date snow conditions call 372-1000. (A. Catamec – 12/19/07)
<写真は昨シーズンのものです・にしむら撮影>
R0012338a.jpg
R0012342a.jpg

Tioga & Glaciar Point Road いまだオープン

12月に入りましたが、Tioga Road と Glaciar Point Road がいまだにオープンしています。
1990年以降では、閉鎖日が12月になった年は1995年だけです。
(閉鎖後に降雪が少なく再オープンし、年末年始時期に通れた年が1年だけあります。)
http://www.nps.gov/yose/planyourvisit/tiogaopen.htm